how is
applied? |
|
|
|
|
set to
challenge the tradition bound construction industry |
|
|
|
|
|
|
|
day one |
step 1 |
|
|
|
|
start -
11:00 |
|
|
|
|
-
moladi
form is delivered to the site. Area = 74m² Mass = 550kg Volume = 4m³
-
start the erection
of
moladi
-
panels are assembled by
general labourers to form the mould/kit of the desired house
plan.
|
|
step
2 |
|
|
|
 |
-
internal panels are
erected.
-
window frames and
block-outs (WinBloc) are positioned.
-
mesh and reinforcing
details are placed according to engineer specifications.
-
external panels are then
erected.
|
|
step
3 |
|
|
|
 |
-
door frames and block-outs
(DoorBloc) are positioned.
-
erection of
moladi
completed.
(4 hours)
-
with only four labourers.
|
|
finish -
15:00 |
|
|
step
4 |
|
start -
15:00 |
|
|
 |
|
|
finish -
17:00 |
|
|
|
|
|
day two |
step
1 |
|
|
|
|
start -
07:00 |
|
|
 |
-
moladi
form is removed.
-
panel being moved weighs less than 30kg
-
(3.84m² X 8kg/m²) and can immediately be
re-erected on the next foundation.
-
removing the
moladi
formwork
complete. (2 hours)
|
|
finish -
09:00 |
|
|
|
|
|
finishing |
|
|
|
step
2 |
|
 |
|
|
|
step
3 |
|
 |
- walls are 1.5 to 2.0 mPa
strong with an ultimate strength of 10 to 20mPa, achieved in 28
days, depending on the mix design of the mortar (C:W Ratio)
- engineer certified roof is
constructed.
|
|
|
step
4 |
|
 |
-
final finishing’s, such as
plumbing and electrical fittings, are completed.
-
structure is now ready for
occupation.
|
|
|
|
|
|
|
|
production
cycle completed in an 8 hour day |
|
|
|
erect
moladi |
-
4 hours |
|
|
|
fill
moladi |
-
2 hours |
|
|
|
remove
moladi
the next day |
-
2 hours |
|
|
|
|
|
|
Copyright © 1990 - 2006 All rights reserved
tsunami emergency
temporary relief United Nations disaster strong quick low cost
housing construction system supplier walls wall walling brick bricks
block cement clc cellular lightweight alternative hurricane black
economic empowerment own business job creation South Africa awards
savings concrete schemes houses structures buildings building
formwork shutter method carcaça custo baixo cubierta bajo costo low
cost affordable sustainable development emergency disaster school
projects tenders prefab shelter plastic homes news books home
classroom clinics earthquake proof resistant technology plans new
journal contractor builder design engineer architect prefabricated
prefab database cast pour production fast track modular training
patented best ties link rod pressure army barracks Afghanistan Sri
Lanka Indonesia India South America Mexico architect Africa war poor
form steel wood decking props adobe straw bale factory export patent
high rise double storey project cheap reinforced steel aid
monolithic
low cost
housing |
|
|
|
|
|
|
|