what labour is required to build a 45 m²house?

 
  • erect moladi - 10 labourers are needed to complete 4 hours work.
  • fill moladi - 7 labourers are needed to, if manually filling the form with buckets, to complete 2 hours work
  • remove moladi - 6 labourers are needed to complete 2 hours work.

Hurricane proof house

 

 

 

  • 2 bedroom

  • bathroom/toilet

  • kitchen

  • lounge

  • profiled IBR sheet roof

the shell is completed in an 8 hour cycle and is hurricane proof and earthquake resistant

one house can be produced in one day with one moladi mould

more houses can be produced in one day with more moladi moulds

Copyright © 1990 - 2008 All rights reserved

house plan lch concrete wall building system moladi hurricane earthquake proof residential housing low cost plastic formwork alternative block development build construction raft foundation mortar south Africa low-cost technology approved nhbrc accredited bank walling structure thermal conductivity decomposed granite plaster quick cheap innovation Thabo Mbeki absa masonry prefabricated steel frame double storey multi level prefab price process patented design house flat high rise form reinforced emergency disaster shutter pour schools clinics awards certified lowcost low cost housing technology www.moladi.com www.moladi.co.za www.moladinamibia.com www.moladipakistan.com www.moladipanama.com www.lowcosthousing.co.za