Formwork | concrete formwork system | formwork construction system

formwork

Formwork

 

Formwork | concrete formwork system | formwork construction system

 

moladi - set to challenge the tradition bound construction industry

 
how is moladi formwork applied? Formwork construction system

 

day one

step 1

   

start - 11:00

 

formwork

form construction

  • moladi formwork is delivered to the site.
    Area = 74m²
    Mass = 550kg
    Volume = 4m³
     

  • start the erection of moladi formwork

  • Designed formwork panels are assembled by general labourers to form the mould/kit of the desired house plan.

 

step 2

 

formwork

Wall building system construction

  • internal panels are erected.

  • window frames and block-outs (WinBloc) are positioned.

  • mesh and reinforcing details are placed according to engineer specifications.

  • external designed panels are then erected.

 

step 3

 

formwork

formwork

  • door frames and block-outs (DoorBloc) are positioned.

  • erection of moladi formwork completed. (4 hours)

  • with only four labourers.

 

finish - 15:00

 

step 4

start - 15:00

 

cast structure formwork

  • four labourers are needed to manually fill the wall cavity with 3.4m³ of an aerated mortar mix.

  • lightweight concrete pour is completed (2 hours)

 

finish - 17:00

 
   

day two

step 1

   

start - 07:00

 

Formwork

Formwork

  • moladi concrete formwork is removed.

  • panel being moved weighs less than 30kg

  • (3.84m² X 8kg/m²) and can immediately be re-erected on the next  concrete foundation.

  • removing the moladi formwork complete.    (2 hours)

formwork system

formwork system

  • moladi concrete formwork example of a larger low cost housing project

  • moladi concrete formwork system is removed.

  • formwork is lightweight

  • Formwork | formwork system | formwork construction system

 

finish - 09:00

 
   

finishing

 
 

step 2

low cost housing

  • structure can be painted with a cementitious water based textured paint as soon as moladi is removed.

  • oil or water based paint can also be used at a later stage.

 

step 3

concrete houses

formwork for concrete houses

  • when moladi form is removed, walls are 1.5 to 2.0 mPa strong with an ultimate strength of 10 to 20mPa, achieved in 28 days, depending on the mix design of the mortar - c:w ratio
  • engineer certified roof is constructed.
 

step 4

formwork design

  • final finishing’s, such as plumbing and electrical fittings, are completed.

  • structure is now ready for occupation.

  • Formwork | formwork system | formwork construction system, concrete formwork, design, formwork supplier, formwork system, concrete forms

 
 

production cycle completed in an 8 hour day

erect moladi concrete formwork

 - 4 hours
fill moladi formwork  - 2 hours
remove moladi  formwork  - 2 hours (the following day)
   

concrete system, construction system, , concrete panels, concrete construction forms, concrete, bednenie, Schalung, cimbras, coffrage, cofragem, Formwork Design products services, form work, m2, square meter,  panels construction