|
|
|||||
|
set to challenge the tradition bound construction industry |
|||||
|
how is
|
|||||
|
|
|||||
|
day one |
step 1 |
||||
|
start - 11:00 |
|||||
|
|
||||
|
step 2 |
|||||
|
|
|||||
|
emergency housing - Wall building system formwork construction |
|
||||
|
step 3 |
|||||
|
|
|||||
|
low cost shelter wall system |
|
||||
|
finish - 15:00 |
|||||
|
step 4 |
|||||
|
start - 15:00 |
|
||||
|
low cost shelter |
|
||||
|
finish - 17:00 |
|||||
|
day two |
step 1 |
||||
|
start - 07:00 |
|
||||
|
low cost shelter Formwork |
|
||||
|
finish - 09:00 |
|||||
|
finishing |
|||||
|
step 2 |
|||||
|
low cost shelter |
|
||||
|
step 3 |
|||||
|
low cost shelter |
|
||||
|
step 4 |
|||||
|
emergency housing low cost shelter |
|
||||
|
emergency housing |
|
||||
|
production cycle completed in an 8 hour day |
|||||
|
erect moladi formwork |
- 4 hours | ||||
| fill moladi formwork | - 2 hours | ||||
| remove moladi formwork | - 2 hours (the following day) | ||||
|
|
|||||